RELOCATION OF TUBAN TERMINAL

Project

OPERATOR – Petrochina Company Ltd (Indonesia)

Project Description

It was required to relocate the Crude Oil Offloading Facilities to deeper water to facilitate Offloading from larger tankers. The new terminal was relocated approximately 1.5km from the existing position. The project involved the installation of a new PLEM, submarine pipeline from existing PLEM to new PLEM, Installation (Mooring) of SPM and FSO.

ZEE’s Scope of Work


ZEE was asked to carry out FEED Study Detail Engineering and prepare the technical documents for RFQ. The study involved the design of

  • Submarine Pipeline,
  • New PLEM,
  • Mooring Analysis,
  • Check the integrity of System and the design of Anchor Piles.
  • Cost Estimation,
  • Compiling Technical documents for RFQ.

Policy Statement

We commit to apply quality management system ISO 9001:2008 and established quality policy as follows:

To comply client requirements and to increase client satisfactory

To produce quality engineering services at competitive rates

To improve the quality of our human resources

Make continuous improvements of the processes, products, services and effective implementation of the quality management system.